It is recommended that the quality control (QC) testing be performed in accordance with the ACR Technical Standard for Medical Nuclear Physics Performance Monitoring of PET Imaging Equipment, as applicable. Data will continue to be collected regarding the QC tests performed by the facility. Based on these data, the ACR Committee on Nuclear Medicine Accreditation may establish QC requirements in the future. At this time, the ACR strongly recommends quarterly testing of each PET system with an appropriate ACR-approved phantom such as described below in addition to other tests recommended by the vendor. At a minimum, testing with the appropriate phantom must be performed semi-annually, but quarterly testing is strongly recommended.


Acceptance Tests 

Initial performance testing of imaging equipment must be performed upon installation and should be completed before clinical use. This testing should be more comprehensive than periodic performance testing and shall be consistent with current acceptance testing practice.

 

Annual Physics Survey 

All tests noted in the PET Equipment Evaluation Summary Form and QC Review (attached below in both pdf and excel formats) must be performed and the form uploaded in the accreditation testing packet. 


A physics survey must be performed on each PET unit at least annually. The ACR realizes that surveys cannot usually be scheduled exactly on the anniversary date of the previous survey; therefore, a period of up to 14 months between surveys is acceptable. A qualified medical physicist (QMP) may perform the testing. Alternatively, testing may be performed by a qualified PET technologist or medical physicist in training approved by the QMP. The test results must be reviewed by the QMP and documented in the annual medical physicist survey report. As a part of the annual survey, the QMP should meet with the supervising physician and the QC technologist to review the results of the survey and the effectiveness of the technologist QC program, and to recommend any corrective action or repairs that are needed. The supervising physician is responsible for assuring compliance with the recommendations of the medical physicist.


The annual physics survey must include the following:

PET Performance Tests
TestDescription
PET Phantom TestingTesting of each PET system with the appropriate ACR-approved phantom and includes tests as outlined in the PET Equipment Evaluation Summary Form and QC Review (attached below in both pdf and excel formats)
Dose CalibratorsAll basic measurements of performance must be done according to protocols accepted by the appropriate state regulatory agencies or the NRC, at the time of installation and repeated after major repair
Dose Calibrator LinearityPerformed quarterly
Dose Calibrator AccuracyPerformed annually

 

Continuous Quality Control

The PET technologist is responsible for verifying day-to-day operation of instruments and performing a few additional tests on a quarterly basis. These requirements represent the standard of practice and are in compliance with requirements and recommendations of The Joint Commission (TJC) and state and federal agencies. Documentation of compliance with all quality control tests and corrective action is required as part of the application process.


PET Technologist's Quality Control Tests
TestDescriptionFrequency
Daily PET Detector CheckPer manufacturer recommendationsEach day of use
Daily CT Check (if applicable) Per manufacturer recommendationsEach day of use
PET Phantom TestingTesting of each PET system with the appropriate ACR-approved phantomSemi-annually (quarterly testing is strongly recommended)
Dose CalibratorsConstancy testDaily


Preventive Maintenance

Preventive maintenance must be scheduled, performed, and documented by a qualified service engineer on a regular basis. Service performed to correct system deficiencies must also be documented and service records maintained by the facility.



Revision History for this Article

Date

Section

Description of Revision(s)

12-12-19

All

Article created; FAQs incorporated; No criteria changes

3-4-21

Annual Physics Survey

Added links to the PET Equipment Evaluation Summary Form and QC Review

3-10-21

Continuous Quality Control

Updated The Joint Commission name

2-4-2022

Continuous Quality Control

Added PET Technologist's Quality Control Tests table with daily PET check and CT check (if applicable). Removed quarterly and semiannual dose calibrator tests.

11-21-2022

Annual Physics Survey

Updated requirements

11-21-2022

Continuous Quality Control

Updated requirements

12-5-2022

All

Attached PET Equipment Evaluation Summary and QC Forms